Summary

When designing its new head office building, the Toronto and Region Conservation Authority (TRCA) intended to use a closed-loop geothermal system for heating and cooling. But subsequent testing led them to pivot to an open-loop system due to its increased environmental benefits and the opportunity to demonstrate the value of this innovative technology.

Background

A worker in safety vest stands next to engineering equipment, with leafy green trees in background

The Toronto and Region Conservation Authority (TRCA) has a mandate to care for the natural environment and protect communities and ecosystems from the impact of flooding and other extreme weather events. Its jurisdiction covers 3,467 km2.

TRCA is building a new head office and has been incorporating sustainability into all aspects of the process, with the aim of achieving a zero-carbon design. The intention is for the building to be both a functional space and a demonstration of green and net-zero construction techniques that can inform and inspire others.

Original plans included a closed-loop geothermal system as an energy-efficient way to provide heating and cooling. However, during test drilling, engineers found they could potentially switch to an open-loop geothermal system or an aquifer thermal energy storage system, both of which can be more energy efficient and cost effective than closed-loop systems but are uncommon in Canada. All of these systems use underground pipes to draw heat from the earth in the winter and expel heat from the building in the summer, but in different ways and with different infrastructure needs.

The challenge

Two workers in safety vests stand on either side of equipment, with leafy green trees in background

While TRCA was prepared to move forward with a closed-loop system, they knew that the discovery of the aquifer presented an opportunity to test the feasibility of the alternatives. The questions were: would an open-loop or aquifer thermal system work for their building? And if so, would it be worth it for them to implement it?

Approach

With financial support from FCM, TRCA decided to do a feasibility study to discover which of the three systems would be the best choice for their site. This included exploratory drilling to answer the following questions:

  1. Is there sufficient groundwater under the site?
  2. Does the groundwater move slowly enough for interseasonal storage of heating and cooling potential?
  3. Is the groundwater chemistry likely to cause scaling or corrosion, which could hinder system performance?

The study also included analysis of the costs, construction-related environmental impact and future energy use of each option.

Results

Two workers in safety vests stand on either side of equipment, with leafy green trees in background

The study showed that any of the options would work on the TRCA building site. TRCA decided to abandon its plans for closed-loop geothermal in favour of an open-loop system for reasons including:

  • Lowest cost, with a savings of approximately 25 percent.
  • Lower emissions from installation and 25-year operation, at 77.8 tCO2e.
  • Less disruption of the surrounding natural environment, in part due to requiring only four open loop boreholes rather than 44 closed loop boreholes.

Benefits

Given TRCA’s mandate to showcase green building technologies, installing a highly functional yet less common open-loop system is an opportunity to share knowledge and advance uptake of this kind of technology.

Lessons learned

TRCA realized they should have done a hydrogeology study initially upon selection of geothermal heating and cooling, rather than embarking on test drilling with only a closed-loop system in mind. Many costs could have been avoided by considering all potential options when test-drilling.

On a regional level, there could be advantages to understanding the underlying geology of specific regions ahead of time to identify high-potential sites for open-loop or aquifer thermal systems.

Next steps

TRCA has moved forward on design and installation of an open-loop system for its head office site. In order to maximize the longevity of this system, they are planning a monitoring and maintenance program that will help them minimize the impact of common issues such as scaling and clogging.

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database