Buildings on the water's edge

The Municipality of the District of Shelburne studied the feasibility of building a local waste transfer station to reduce the costs and environmental impact of trucking waste to a landfill in another municipality. 

Under a shared service agreement, the district also provides collection and disposal for the Town of Shelburne and the Town of Lockeport. Once filled, the curbside collection trucks, better suited to short hauls, make a three-hour return trip to the landfill. A transfer station would allow specially-designed long-haul trucks to make the trip to the landfill.

Building a waste transfer station would reduce fuel consumption. It would, however, provide economic benefits only if two neighbouring municipalities (the District of Barrington and the Town of Clark's Harbour) participated in the project.

Results

Environmental Economic Social
  • Fuel consumption from truck travel to and from the landfill would be reduced by about one-third
  • The transfer station system would be cost-effective if five municipalities participated
  • An awareness campaign to promote separation of recyclable and compostable waste would further reduce landfill use

Challenges

  • Finding a suitable location for a waste transfer station.
  • Estimating financial savings in the face of changing energy prices.
  • Familiarizing outside consultants with the needs of the rural community.

Lessons learned

  • Engage staff in the early stages of any feasibility study.
  • Make sure all quantities included in the analysis, such as amount of fuel used, are adequately researched.
  • Make sure that the process for evaluating the technical and economic feasibility is defined clearly and early.
  • Use the skills of the steering group.

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

Taking sediment samples

To reduce economic and environmental costs, the District of Squamish tested sediment in a nearby ocean channel for use as fill in a major waterfront redevelopment project.

If safe, sediment from the Mamquam Blind Channel would be a convenient source of filling to develop a park in a project by Squamish Oceanfront Development Corp. The project would transform a former 59-acre industrial site into a peninsula of neighbourhoods, parkland and beaches.

The sediment passed the purity tests, avoiding the need for 20,000 truckloads of material to be delivered from a site 15 kilometres away. It provides an environmentally friendly, less costly source of clean fill for the new development.

Results

Environmental Economic Social
  • 230,000 m3of trucked-in fill replaced by safe-for-use ocean sediment near the site

  • 300,000 km of GHG-generating truck travel avoided

  • Sediment will form a clean cap over contaminated soil in former industrial site

  • Using sediment as fill eliminates trucking costs

  • Project site provides a place for sediment that must be dredged periodically to keep the channel navigable

  • New park will encourage tourism, recreation, commerce and economic development

  • 7.5-acre park will be created with sediment fill

  • A waterfront community will be developed with ample space for arts and cultural activities, sports and recreation, and a marina

Challenges

  • Assuring sediment was free of mercury and hydrocarbon contamination from an old chlor-alkali processing plant.
  • Finding staff time for up to 70 hours of work in writing grant applications and reports.

Lessons learned

  • Review reports and interview former occupants of test sites to identify areas of potential contamination.
  • Where possible, use divers, not barge-based drill rigs, to collect sediment samples. They cost less and are more flexible.
  • Costly anti-pollution checks are worth the money; they clear the way for profitable economic redevelopment.

Resources

Partners and Collaborators

Project Contact

Heather Dunham
Manager, Squamish Oceanfront Development Corp.
District of Squamish, BC
T. 604-815-5075

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

International Peace Bridge

To give itself new opportunities and a new look, the Town of Fort Erie drafted a brownfield revitalization plan that offers developers tax and other incentives to clean up and redevelop more than 250 acres of vacant, abandoned, and possibly contaminated industrial sites.

The town, connected to Buffalo, New York, by the International Peace Bridge over the Niagara River, was once a bustling commercial centre, home to aircraft and chemical factories, steel plants and lumber yards. Now manufacturing has given way to a tourism and service economy, leaving the urban landscape studded with unsightly scenes of industrial dereliction.

To rectify this, the town commissioned studies on brownfield remediation and the economic, environmental and social benefits that would flow from it. Then it adopted a plan that will not only provide financial incentives for private redevelopment but also encourage the town itself to lead the way by reclaiming and rebuilding brownfield sites it owns.

Results

Environmental Economic Social
  • Redevelopment tax breaks are tied to energy-efficient building standards

  • Brownfield remediation decontaminates soil, stops water pollution

  • $1.2 million increase in property tax revenue from redeveloped brownfields

  • 600 new jobs from cleanup and redevelopment work

  • Reclaimed brownfields reduce urban sprawl, provide space for new housing

  • Brownfield redevelopment creates more attractive, liveable neighbourhoods

Challenges

  • Convincing skeptical property owners and developers that tax and grant incentives are rich enough to make brownfield remediation and redevelopment profitable.
  • Convincing skeptical ratepayers that tax holidays and breaks for brownfield developers will generate higher tax revenue in the future.
  • Spurring development in a town with a limited economic base.

Lessons learned

  • Allow ample time to review draft reports from consultants to keep the process moving expeditiously.
  • Be prepared for pressure before the plan is finished from investors and sellers looking to know how remediation incentives might affect business deals.
  • Public information meetings help generate investor interest in brownfield cleanup work.

Resources

Partners and collaborators

Project Contact

David Heyworth
Senior Policy Planner
Fort Erie, ON
T. 905-871-1600 ext. 2504

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

The City of Kamloops evaluated the extent of soil and groundwater contamination on a portion of the municipally-owned site of the former provincial Rayleigh Correctional Centre. Previously a Department of National Defence munitions depot, the site had also been used for waste oil drum and coal storage, an incinerator, a fire pit and a landfill.

The study identified contaminants in 5,000 cubic metres of soil and outlined a remediation plan. The contaminated soil was used for road construction, buried on site or removed. Sampling determined that the groundwater did not require remediation, as its quality was comparable to water elsewhere in the valley.

The city built the Tournament Capital Ranch on the site in 2011. It features eight baseball diamonds and two rugby fields. Future development may include an exhibition/agri-plex building and equestrian facilities. The Tk'emlups First Nation is making plans for an RV park, and a portion of the land has been retained for agricultural use.

Results

Environmental Economic Social
  • 5,000 m3 of soil remediated

  • 80 ha of land remediated

  • 300,000 honey bees successfully relocated

  • Habitat along North Thompson River protected

  • 44 ha of land available for agricultural use

  • Potential development of exhibition/agri-plex and equestrian facilities

  • RV park planned by Tk'emlups First Nation

  • Weekly tournaments drawing hundreds of spectators and participants

  • Gathering place for agricultural exhibitions

  • 5 km of walking paths

  • Opportunities for health-promoting recreational activities

Challenges

  • The city found munitions-related debris from the World War II era. Removal of this material required the involvement of the Department of National Defence and the Canadian Forces.
  • Additional work was required to meet stringent agricultural and water-quality standards.
  • Provincial Ministry of Environment standards, guidelines and regulations changed during the project.
  • Some waste was deemed hazardous and had to be taken to a more distant landfill at additional cost to the city.

Lessons learned

  • Allocate time and resources for unanticipated issues, particularly with large, complex projects.
  • Deal with issues as they arise, and don't take short-cuts.
  • Ensure that all stakeholders-including city council, senior management, staff, project team members and the public-understand the remediation process.
  • Work with local consultants to reduce travel costs and provide flexibility for the project team.
  • Use city staff for tasks such as soil removal, to save time and money.

Resources

Project Contact

Nick DeCicco
Parks Project and Planning Supervisor
Parks, Recreation & Culture
City of Kamloops, British Columbia
T. 250-828-3518

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

Duffering county courthouse

Dufferin County is considering an energy-from-waste solution for its garbage. The county studied a plasma gasification technology that converts waste into electricity, examining two options — 50,000-tonnes-and 70,000-tonnes per year — that might be large enough to be economical. Only the larger option, which could reduce landfill waste by 200 to 250 tonnes per day, was found to be feasible. It would divert as much as 90 per cent of waste from the landfill and avoid the cost of building a new landfill or of trucking waste outside the municipality.

Results

Environmental Economic Social
  • Diverts 200 to 250 tonnes of solid waste from the landfill each day
  • Increases the county's waste diversion rate to as much as 90%
  • Provides stable long-term pricing for disposal of municipal waste
  • Feeds electricity into the power grid
  • Avoids capital cost of developing new landfills
  • Dufferin deals with its own garbage, rather than transferring waste to neighbouring communities
  • Makes Dufferin a leader in responsible waste management and electricity generation.

Challenges

  • The cost of a feasibility study for a waste management project - especially for a fairly new technology - is challenging for a small municipality.

Lessons learned

  • Build for the future. If a 50,000-tonne facility is needed now, build to a 70,000-tonne capacity and find someone who needs to manage 20,000 tonnes a year until the volume ramps up.
  • The team should have dropped the smaller option from the study as soon as it was clearly not viable. That would left more resources for investigation of the more ambitious option.

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

Côte-de-Beaupré aims to be a healthy region

Bucolic scenery at Saint-Tite-des-Caps

To support long-term community planning, the Côte-de-Beaupré Regional County Municipality (MRC) has produced an integrated sustainability plan. The outcome of a major public consultation process, the plan is integrated, practical and inclusive. It consists of a mobilization plan, two-stage sustainability strategic plans, and a sustainable development plan. These guides will enable the MRC to protect the environment, diversify its economy and improve citizens' quality of life.

This master plan for sustainability replaces the existing development plan. Local municipalities will be required to amend their urban planning bylaws to comply with the vision and development orientations defined in the new regional plan.

Results

Environmental Economic Social
  • The action plan contains realistic sustainable development projects for the region.

  • Strategic planning deals with issues specific to Côte-de-Beaupré and will guide regional development.

  • The plan will allow the MRC to ensure that investments are prudent and profitable.

  • Most of the MRC's savings result from using available resources to facilitate partnerships with government and other organizations.

  • The strategic plan will create synergies between stakeholders and encourage innovative, popular projects.

Challenges

  • The MRC had difficulty obtaining buy-in from stakeholders but invested time and energy in circulating information about its approach, project progress, planned activities and achievements. Its perseverance brought most of the public on board, and created ambassadors in various business sectors.

Lessons learned

  • The process should be completed quickly to maintain the interest of elected officials, local stakeholders and the public. 
  • Obtain commitment at the outset from key parties as their strengths and skills will influence the dynamics of every consultation activity.
  • In  public consultations, show people actual components even if they are incomplete, to elicit. better informed, more constructive input.
  • Developing the sustainability plan internally gave the MRC experience and confidence that will be useful in other projects.

Partners and Collaborators

Project Contact

Gitane St-Georges
Sustainability Officer
Côte-de-Beaupré RCM, QC
Château-Richer, QC
T. 418 824-3420, ext. 239

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

Municipal wastewater systems release more than six billion cubic meters of effluent into waterways each year. Municipalities working to improve the quality of their effluent face significant challenges in upgrading aging infrastructure to comply with increasingly stringent provincial and federal regulations.

This series provides a framework to help municipalities develop innovative and sustainable wastewater system projects. The articles draw on proven lessons from a dozen of the successful wastewater treatment studies and projects that FCM's Green Municipal Fund (GMF) has funded.

Practical tips you can use to guide your project

The articles cover specific, hands-on tips for the three key phases of a successful wastewater plant project:

  1. Project scoping and stakeholder engagement
  2. Project planning and design
  3. Procurement, construction and start-up

In each article, you'll find:

The project checklist highlights important points to consider at each step. Use the checklist as a guide to ensure that you are addressing the key issues during each phase of your project.

Did you find this page helpful?
Please offer suggestions that will improve the learning center for you:

The Town of Lockeport developed an integrated community sustainability plan in collaboration with its citizens to guide its environmental, social, cultural and economic development for 30-plus years. Lockeport is a tiny, isolated town on Nova Scotia's south shore. While rich in cultural heritage, it is dealing with limited financial resources, an aging population, and a fishing industry that is no longer the economic engine it once was. The area is also feeling the impacts of climate change, including extreme weather events.

The plan outlines ways to boost tourism, revitalize local commerce, reduce reliance on cars and protect the natural environment, among many other goals. The plan will help the town think more creatively about how to build a sustainable Lockeport and reduce its environmental footprint.

Results

Environmental Economic Social
  • Plan aims to reduce greenhouse gas emissions by 10 per cent by 2040
  • Establishment of a flood plain zone to adapt to extreme weather events
  • Limits on development will protect environmentally sensitive areas
  • A fisheries training school/marine centre of excellence will help revitalize a key industry
  • A permanent venue for the town's several festivals will increase tourism
  • Improvements to transportation links will reduce the isolation and boost the economy
  • Promotion of active transportation will foster a healthier community
  • Commercial revitalization will make the town a more vibrant place to live

Challenges

  • Limited financial resources has led to constraints on new initiatives.
  • Developing a diverse, vibrant local economy is difficult in a geographically isolated region.

Lessons learned

  • Community participation is a must, so knock on as many doors as possible in the development of the plan.
  • Be aware of the amount of time staff will need to develop the plan.

Resources

Partners and collaborators

Project contact

Bil Atwood
Project Manager
Lockeport, NS
T. 902-656-2209

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

This is part of a series of case studies on wastewater projects funded by the FCM's Green Municipal Fund. Each case study provides technical information, project details and tips on best practices.

Project overview

The City of Cranbrook, BC, updated its wastewater treatment system with a new storage pond, two new disinfection facilities and upgrades to its aerated lagoon. The $29 million project includes retrofits to modernize an agricultural irrigation system that reuses wastewater. Fine bubble aeration and UV disinfection help reduce total suspended solids (TSS), biochemical oxygen demand (BOD) and phosphorus levels and improve the quality of wastewater.

To ensure optimum value over the life of the project, the City participated in a value engineering planning exercise, did full-cost accounting and installed process automation features. The upgraded system provides tertiary treatment to the current population of 19,319 and has the capacity to serve 40,000. 

The figure illustrates the timeline of the initiative in the City of Cranbrook, BC, depicting “time projected”, “time over” and “actual time”. The detailed design was projected to take 21 months to complete, starting in April 2009. The actual time to complete it was 31 months, and the completion date was October 2011. The initiative was delayed by 10 months. The first part of the figure illustrates the population served by the wastewater initiative. In the City of Cranbrook, BC, the wastewater treatment plant serves 19,319 people. The second part of the figure illustrates the budget of the initiative. The amount required to complete the initiative was projected to be $26 million. The amount actually required was $29 million. The initiative was over budget by $3 million. The figure shows the Total Suspended Solid (TSS) in the water treated by the City of Cranbrook, BC, initiative. Before the initiative, the TSS was 250 mg/L. After the initiative, the TSS decreased by 98% to 5 mg/L.

Reasons for the project

  • A ruling from the BC Environmental Appeal Board (1999) required Cranbrook to create an outfall into the Kootenay River and manage the water levels in one of its treatment lagoons.

Innovative aspects of the project

  • The project design made excellent use of systems thinking.
  • The system is simple and uses a low-tech approach that is appropriate for a municipality bordering on agricultural lands.
  • The upgraded facility makes use of reclaimed water for agricultural application.   

Best practices and key lessons

The municipality's experience with this project demonstrates some best practices and key lessons that can inform similar projects.

Develop a long-term vision

  • Instead of making piecemeal adjustments simply to achieve minimum thresholds, Cranbrook reviewed the entire system and created a long-term vision for wastewater treatment in the community.
  • The city's vision was to become a model of excellence in the use of reclaimed wastewater. This drove short-term planning and generated support from funders and community members. 

Engage early and broadly

  • The municipality overcame an initial lack of public interest in the project by building relationships with the community, including surrounding rural areas, stakeholders, provincial agencies and First Nations.
  • Cranbrook conducted a preliminary archaeological assessment, engaged in dialogue with local First Nations, held open houses, offered tours and updated council regularly.
  • These efforts allowed the city to engage with the community as a whole and to address criticisms of past operating practice and negative perceptions of the project.

Conduct background research

  • Cranbrook conducted extensive research, including feasibility and pre-engineering studies, during the pre-design process.
  • The updated wastewater treatment system uses existing technology in an innovative way that leverages natural systems and processes. For instance, to reduce runoff from irrigation, the system uses low-pressure sprinklers rather than impact sprinklers.

Optimize long-term returns on investment

  • To ensure an optimal return on investment, the leadership group involved in the project participated in a value engineering exercise at the design stage.

Aerial view of City of Cranbrook, BC. Image shows mountains in background, city and the wastewater treatment plant.
City of Cranbrook, BC

Project benefits

This project yielded a number of environmental, social and economic benefits. 

Environmental benefits

Lower energy usage: The city increased the plant's energy efficiency by replacing high-pressure irrigation heads with low-pressure components, removing pipeline restrictions to reduce the pumping energy required, and installing centralized and automated monitoring pivot irrigation systems.

Reduced greenhouse gas (GHG) emissions: The city replaced three cells in facultative treatment lagoons and converted a facultative effluent storage pond to a high-efficiency bubble diffusion aeration system. These upgrades have reduced the facility's GHG emissions.

Improved wastewater quality: Effluent now meets provincial Ministry of Environment regulatory requirements.

Reduced water consumption: High-efficiency spray nozzles has improved irrigation efficiency and improved absorption, thus reducing irrigation-application rates.  

Elimination of chemical residuals: Because UV technology has replaced chlorination as a means of disinfection, the amount of chlorine in effluent is reduced.

Ecosystem protection: Higher-quality effluent leads to healthier wildlife, vegetation and marine life. In addition, the city built a storage pond to avoid accidental spillage of partially treated sewage into a nearby creek.

Reduced odour levels: Odour is reduced through the use of fine bubble diffusers in lagoon cells. Complaints from nearby residents and businesses have been eliminated. 

Social benefits

Improved public heath: Residents' health is protected through improved water quality and reduced GHG emissions.

Increased opportunities for recreational and physical activity: Because effluent used for irrigation of feedstock fields is disinfected, these irrigated areas are safe to enter. The public now has access to approximately 2,500 acres of land for recreational and physical activities such as bird watching, dog walking, hiking, cross-country skiing and hunting.

Increased level of service to the community: In addition to improving water quality, the upgrades increased wastewater treatment capacity. The upgraded plant will accommodate population growth for at least 20 more years.  

Increased civic pride: Residents show an increasing sense of civic pride and ownership when discussing the attributes of the community.

Municipality recognized for leadership in sustainability: Increasingly, the city is perceived throughout Western Canada as a leader in the treatment of sewage and its reuse in an environmentally responsible manner.

Economic benefits

Reduced maintenance costs: Annual maintenance costs will be reduced because the new equipment will require fewer repairs.

Support for new economic development: The wastewater treatment plant will be able to accommodate commercial and industrial development for a period of 20 years or longer. The improvements resulting from the project will attract new businesses to the area.

Support for residential growth: The wastewater treatment plant will be able to accommodate population growth and additional housing for a period of 20 years or longer.

Support for local business: The city installed new spray technologies on about 28 irrigation pivot systems to water close to 1,800 acres of feedstock fields. This increases crop production and supports the local beef cattle production. Without this source of nutrient-rich water, this industry would not be able to exist in this semi-arid region.

Local job creation: System upgrades have increased irrigation potential and crop yields, creating growth and jobs in the local ranching sector.

Improved operational efficiency: Installation of a SCADA (Supervisory Control and Data Acquisition) system provides a reliable monitoring mechanism and significantly facilitates data retrieval, which can be done remotely.

Development of new partnerships: This project has enabled a potential future partnership with Ducks Unlimited Canada (DUC) to supply effluent to the DUC Oxbow waterfowl nesting and refuge area (approximately one million cubic metres of effluent annually). This would help to maintain sufficient water volume within the Oxbow.

The figure uses a pie chart to show the funding breakdown of the City of Cranbrook, BC, wastewater initiative by source of funding. This includes: federal: 58%; municipal: 29%; GMF loan: 11%; and GMF grant: 2%.

Technical highlights

Technical highlights are current as of 2013.

Treatment

  • Before: Aerated lagoon
  • After: Aerated lagoon with increased on-site storage and permanent outfall structure on the Kootenay River

Disinfection

  • Before: None — 200 CFU/100mL
  • After: UV disinfection system — <1 CFU/100mL

Biosolids management

Biosolids build up in the lagoon. They are removed every seven to ten years and used for agricultural application.

Average annual daily flow (AADF)

  • Before: 11.7 MLD (million litres per day)
  • After: 8.0 MLD

Biochemical oxygen demand (BOD)

  • Before: 30 mg/L 
  • After: 10 mg/L 
     

Project contact information

Joe McGowan
Director, Infrastructure Planning & Delivery
City of Cranbrook, BC
T. 250-489-0240

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

This is part of a series of case studies on wastewater projects funded by the FCM's Green Municipal Fund. Each case study provides technical information, project details and tips on best practices.

Project overview

The City of Barrie, ON, expanded its wastewater treatment plant to accommodate municipal growth and improve the quality of water flowing out of the plant and into the environment. The project expanded the plant's capacity for water pumping, biological treatment, solid separation, disinfection, sludge digestion and beneficial use of biogas. The city also added a new anoxic selector tank.

These upgrades have reduced the amount of phosphorus in the wastewater and helped to maintain acceptable levels of ammonia. The upgrades have also increased the plant's production of biogas, which is used for on-site generation of electricity to reduce energy costs. In addition, the project has contributed to the continued protection of Kempenfelt Bay and Lake Simcoe. 

The figure illustrates the timeline of the initiative in the City of Barrie, ON, depicting “time projected”, “time over” and “actual time”. The detailed design was projected to take 5.5 years to complete, starting in late 2005. The actual time to complete it was 6 years, and the completion date was November 2011. The initiative was delayed by 6 months. The first part of the figure illustrates the population served by the wastewater initiative. In the City of Barrie, ON, the wastewater treatment plant serves 135,711 people. The second part of the figure illustrates the budget of the initiative. The amount required to complete the initiative was projected to be $84 million. The amount actually required was $87.9 million. The initiative was over budget by $3.9 million. The figure shows the Biochemical Oxygen Demand (BOD) in the water treated by the City of Barrie, ON, initiative. Before the initiative, the BOD was 5.6 mg/L. After the initiative, the BOD decreased by 71% to 1.6 mg/L.

Reasons for the project

  • The city needed to increase the capacity of its wastewater treatment plant to support community growth and minimize combined sewer overflows.
  • The system also needed upgrades to ensure that effluent would meet the standards for ammonia and phosphorus loadings set out in the Lake Simcoe Protection Plan (2009).

Innovative aspects of the project

  • Barrie's wastewater treatment plant is the largest point of discharge in a sensitive, freshwater environment.
  • This project has contributed to the ongoing restoration and protection of Lake Simcoe.   

Best practices and key lessons

The municipality's experience with this project demonstrates some best practices and key lessons that can inform similar projects.

Conduct background research

  • One lesson learned was that the project would have benefitted from additional research on regional environmental trends and requirements, such as more stringent standards for phosphorous levels and effluent.
  • By consulting with regulators and interest groups, including conservation authorities, the city engaged stakeholders to learn how others were tackling these issues and what new technologies were available to treat phosphorous. 

Optimize long-term returns on investment

  • The city undertook a value engineering process with the successful bidder to identify opportunities to improve the project design and reduce costs.

Use alternatives to lowest-bid procurement

  • The city's engineering department and the design consultant worked together to pre-qualify bidders and used a quality-based selection process to evaluate the bids (versus using a lowest-bid procurement method).
  • The city pre-selected major equipment, including raw sewage pumps, tertiary filters and UNOX tank mixers.

Use effective communications and project management

  • Barrie's wastewater operations group was involved throughout the planning, design and commissioning of the upgraded facility.

Prepare detailed testing and commissioning work plans

  • Detailed testing and commissioning work plans should be developed during the early stages of a major project.
  • During the design process, the project team worked to identify potential shutdowns that would cause service disruptions.
  • Project timelines should reflect the time required for biological processes to become established and respond.

Image of rotating biological contactors in City of Barrie, ON.
Rotating biological contactors installed to reduce ammonia and organic nitrogen in Kempenfelt Bay (City of Barrie, ON). 

Project benefits

This project yielded a number of environmental, social and economic benefits. 

Environmental benefits

Reduced energy consumption (electricity and natural gas): The city added variable frequency drives, which ramp up and slow down motors depending on requirements, reducing electrical demands.

Renewable energy generation: The plant generates more biogas as fuel because it is treating more wastewater. This allows boilers and co-generation engines to run more consistently (rather than intermittently) to generate heat and electricity for various treatment processes and winter heating.

Improved effluent quality: The city is able to comply with more stringent effluent treatment requirements. Effluent quality meets the Environmental Compliance Approval (ECA) targets set by the Ontario Ministry of the Environment and Climate Change. For phosphorus and ammonia, the targets are 0.18 mg/L and 4-10mg/L respectively (monthly averages).

Decreased municipal water consumption and improved stormwater management: As part of this project, the city implemented several complementary programs to help reduce the treatment plant's wastewater inflow load. These included a comprehensive inflow and infiltration (I&I) program, a low-flow toilet rebate program and a review of illegal roof drainage systems and downspout connections.

Improved odour control: The city added a new biological odour control unit to treat air collected from the truck loading station, sludge blending tanks and sludge holding tank.

Social benefits

Improved staff health and safety: The facility was nearing its hydraulic capacity, and therefore the equipment and tanks were nearing their capacities. Expansion of various process tanks has improved operators' ability to make small adjustments over longer periods of time.

The expansion also allowed for tanks to be removed from service for maintenance activities, which ensures continuous service and reduces maintenance closures for the wastewater treatment plant. Permanent cranes were also added to give staff the ability to lift heavy objects more safely; previously they used winches and chains.

Opportunities for physical and recreational activities: The project's new odour control unit has minimized odours emanating from the wastewater treatment plant. This in turn encourages more use of the waterfront.

Promotion of a sustainable lifestyle: The expansion project demonstrates Barrie's commitment to creating a vibrant downtown, managing growth through intensification and protecting the environment and health of Lake Simcoe.

Public space: A healthy Kempenfelt Bay is a showcase for Lake Simcoe and an important centrepiece of the community.

Economic benefits

Improved conditions for tourism: A cleaner waterfront increases the city's ability to attract tourists, who generate revenue for area businesses.

Support for economic growth: The facility's expanded treatment capacity allows for further intensification in the city's land use, creating supportive conditions for economic growth, employment and municipal revenue.

Diverse sources of financing: The city was able to finance this project through revenue from utility rates and development charges, as well as through interim financing, debentures and a Green Municipal Fund grant and loan.

Decreased operating costs: The city installed high-efficiency motors for all pumps and mixers and high-efficiency UV bulbs to make the existing UV system more energy-efficient. The existing hydronic heating system, which uses the wastewater biogas for fuel rather than electricity or natural gas, was expanded, thus increasing energy efficiency.

Extended asset service life: The project expanded the capacity of the existing facility, saving the expense of building a new one.

The figure uses a pie chart to show the funding breakdown of the City of Barrie, ON, wastewater initiative by source of funding. This includes: municipal: 97%; GMF loan: 2%; and GMF grant: 1%.
 

Technical highlights

Technical highlights are current as of 2013.

Treatment

  • Before: Conventional activated sludge
  • After: Conventional activated sludge with a UNOX system and rotating biological contactors

Disinfection

  • Before: UV disinfection system
  • After: The project added a secondary, high-pressure sodium UV system to supplement the existing UV system, which had not yet reached the end of its life cycle.

Biosolids management

Biosolids that build up in the lagoon are removed every seven to ten years, and used for agricultural application.

Average annual daily flow (AADF)

  • Before: 52.9 MLD (million litres per day)
  • After: 51.2 MLD

Design capacity

  • Before: 57.1 MLD
  • After: 76.0 MLD

Per cent of total capacity used for AADF

  • Before: 93 per cent
  • After: 68 per cent

Total suspended solids (TSS)

  • Before: 5.6 mg/L
  • After: 1.5 mg/L
     

Project contact information

Jessica Peters-Palfi
Senior Engineer
City of Barrie, ON
T. 705-739-4220, ext. 4740

Michael Jermey
Deputy Treasurer
City of Barrie, ON
T. 705-739-4220, ext. 4751

Want to explore all GMF-funded projects? Check out the Projects Database for a complete overview of funded projects and get inspired by municipalities of all sizes, across Canada. 

Visit the projects database

Pagination

Subscribe to